What is CEQA?
CEQA stands for the California Environmental Quality Act.
What is changing from the typical CEQA process?
For this project, the typical CEQA administrative process will be waived. This saves six (6) to nine (9) months in project planning time because certain tasks like initial field surveys, clearing house filings, and challenge periods will not be needed. The project will still conform with the Environmental Protection Plan.
Is there an updated I-280 project timeline?
What other state projects have been approved under the Governor’s Emergency Proclamation on March 1, 2025?
For approved projects, visit the Approved Projects Dashboard.